WREP & SCPx ROW - Surface Drainage Arrangement
WREP & SCPx ROW - Surface Drainage Arrangement
The project involved the design and construction of geotechnical risk reduction measures for eroded areas and landslides at eight locations along the WREP and SCPx oil and gas pipelines. The scope of works included the development of detailed remediation designs and the subsequent installation of approximately 1,700 m³ of Reno mattresses and gabion walls, as well as riprap placement and berm construction. In parallel, comprehensive environmental assessments were carried out, including Environmental and Social (E&S) Risk Assessments, followed by the preparation and implementation of site-specific re-cultivation plans. All works were successfully completed in accordance with applicable environmental, safety, and engineering standards.